The City of San José has prepared an Addendum to the San José Downtown Strategy 2040 Final Environmental Impact Report (FEIR) as supplemented and addenda thereto, for:
Project File No. and Name: H20-021, Almaden Boulevard Tower Project
Location: 50 South Almaden Boulevard, east side of South Almaden Boulevard, between Post Street and West San Fernando Street
Director’s Hearing Date: Wednesday, December 9th, 2019
The Addendum is posted on the City’s website at: http://www.sanjoseca.gov/ActiveEIRs
Project Description: Site Development Permit to allow construction of a new 20-story plus penthouse commercial office building, approximately 781,000 gross square feet in size, including 11,750 sf of ground-floor active use with four stories of underground parking and four stories of above-grade parking, and the removal of eight ordinance size trees and one non-ordinance size tree on an approximately 0.99-gross acre site.
If you have any questions, please contact the Environmental Project Manager below:
Kenneth Rosales